India is in the midst of a rapid expansion in coal-fired power plant capacity. According to an August 2011 study by Prayas Energy Group, 590,000 megawatts (MW) of projects have received or are expected to receive environmental clearance.[1] The table below provides information on 554 proposed projects representing 617,399 MW of capacity and an estimated 3.7 billion tons of annual carbon dioxide emissions. For information on individual plants, click on the map or on the name of the plant in the sortable table below. For information on mining, power sector companies, financing, environmental impacts, citizen opposition, and other coal-related topics, see India and coal.
| State |
Plant |
Company |
MW |
Annual CO2 (tons) |
Type |
Status |
Year |
| Andhra Pradesh |
Adilabad Power Station Unit 1 |
Singareni Collieries |
600 |
3,548,220 |
|
Construction |
2012 |
| Andhra Pradesh |
Adilabad Power Station Unit 2 |
Singareni Collieries |
600 |
3,548,220 |
|
Early development |
2016 |
| Andhra Pradesh |
Adilibad power station (Shalivahana Power Corp.) |
Shalivahana Power Corp. |
300 |
1,774,110 |
|
Uncertain |
|
| Andhra Pradesh |
Ankulapatur power station phase 1 |
VSF Projects |
350 |
2,069,795 |
Supercritical |
Construction |
|
| Andhra Pradesh |
Ankulapatur power station phase 2 |
VSF Projects |
135 |
798,350 |
Supercritical |
Planning |
|
| Andhra Pradesh |
Pynampuram Thermal Power Project Units 1 and 2 |
Thermal Powertech Corporation |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2014 |
| Andhra Pradesh |
Bhavanapadu Thermal Power Project (Kakarapalle) |
East Coast Energy |
2640 |
15,612,170 |
Supercritical |
Deferred |
|
| Andhra Pradesh |
Bhavavipuram Cement power station |
Deccan Cements |
18 |
106,447 |
|
Construction |
|
| Andhra Pradesh |
Budele power station |
Indu Projects Limited |
1000 |
5,913,701 |
|
Unconfirmed |
|
| Andhra Pradesh |
Damodaram Sanjeevaiah Thermal Power Station (Krishnapatnam) |
Andhra Pradesh Power Generation Corporation (APGENCO) |
1600 |
9,461,921 |
Supercritical |
Construction |
2013 |
| Andhra Pradesh |
Damodaram Sanjeevaiah Thermal Power Station (Krishnapatnam) expansion |
Andhra Pradesh Power Generation Corporation (APGENCO) |
2400 |
14,192,911 |
Supercritical |
Cancelled |
|
| Andhra Pradesh |
Dharmavaram power station |
Nava Bharat Ventures Ltd |
150 |
887,055 |
|
Deferred |
|
| Andhra Pradesh |
Dr. RKP Power Ankulapatur power station phases 1 and 2 |
Dr. RKP Power |
430 |
2,542,891 |
|
Advanced development |
|
| Andhra Pradesh |
Garividi power station |
Facor Power |
45 |
266,117 |
|
Construction |
|
| Andhra Pradesh |
Gopuvanipalam Mega Thermal Power Project (Chinnapuram, Machilipatnam) |
Nagarjuna Construction Company |
1980 |
11,709,128 |
Supercritical |
Unconfirmed |
|
| Andhra Pradesh |
Gudur Thermal Power Project (Momidi) Phases I and II |
Pragdisa Power Private Ltd |
2640 |
15,612,170 |
Supercritical |
Planning |
|
| Andhra Pradesh |
Gunipudi power station (NBPL proposal) |
Namratha Bizili Private Limited |
300 |
1,774,110 |
|
Deferred |
|
| Andhra Pradesh |
Gunipudi power station (STEAPL proposal) |
Suryachakra Group |
1320 |
7,806,085 |
Ultra Supercritical |
Advanced development |
|
| Andhra Pradesh |
Hindupur power station |
Sheshadri Power & Infrastructure |
1320 |
7,806,085 |
|
Unconfirmed |
|
| Andhra Pradesh |
Jaipur power station |
Singareni Collieries |
600 |
3,548,220 |
|
Construction |
2013 |
| Andhra Pradesh |
Jharapudi power station |
Suryachakra Group |
140 |
827,918 |
|
Unconfirmed |
|
| Andhra Pradesh |
Kakatiya Thermal Power Project Stage-II |
Andhra Pradesh Power Generation Corporation (APGENCO) |
600 |
3,548,220 |
|
Construction |
2012 |
| Andhra Pradesh |
Kineta Power Stage I (Krishnapatnam) |
Kineta Power Limited |
1320 |
7,806,085 |
Supercritical |
Advanced development |
|
| Andhra Pradesh |
Kineta Power Stage II (Krishnapatnam) |
Kineta Power Limited |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Andhra Pradesh |
Komarada power station |
Alfa Infraprop Pvt. Ltd. |
2640 |
15,612,170 |
Supercritical |
Planning |
|
| Andhra Pradesh |
Kotapally power station (SKIL Group) |
SKIL Group |
600 |
3,548,220 |
|
Unconfirmed |
|
| Andhra Pradesh |
Kothagudem Phase V Unit 10, Phase VI Unit 11 |
Andhra Pradesh Power Generation Corporation (APGENCO) |
1000 |
5,913,701 |
|
Newly commissioned |
2011 |
| Andhra Pradesh |
Kothagudem TPS expansion |
Andhra Pradesh Power Generation Corporation (APGENCO) |
800 |
4,730,961 |
|
Planning |
|
| Andhra Pradesh |
Krishnapatnam Navayuga thermal station Phase I |
Navayuga Power |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2014 |
| Andhra Pradesh |
Krishnapatnam Navayuga thermal station Phase II |
Navayuga Power |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Andhra Pradesh |
Krishnapatnam Ultra Mega Power Project 1-2 |
Reliance Power |
1320 |
7,806,085 |
|
Deferred |
2013 |
| Andhra Pradesh |
Krishnapatnam Ultra Mega Power Project 3-6 |
Reliance Power |
2640 |
15,612,170 |
|
Deferred |
2015 |
| Andhra Pradesh |
Latchayapeta power station |
NCS Sugars Ltd. |
600 |
3,548,220 |
|
Planning |
|
| Andhra Pradesh |
Lovapalem power station |
My Home Power Ltd. |
1000 |
5,913,701 |
|
Unconfirmed |
|
| Andhra Pradesh |
Meenakshi Energy Thermal Power Project Phase-I |
Meenakshi Energy |
300 |
1,774,110 |
|
Construction |
2012 |
| Andhra Pradesh |
Meenakshi Energy Thermal Power Project Phase-II |
Meenakshi Energy |
600 |
3,548,220 |
|
Advanced development |
2013-2014 |
| Andhra Pradesh |
Meghavaram Kakarapalli power station |
Meghavaram Power |
450 |
2,661,165 |
|
Deferred |
|
| Andhra Pradesh |
Muthukur Mandal power station (Painampuram) |
Nelcast Energy Corporation Ltd |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Andhra Pradesh |
Nagarjuna Construction Company Sompeta Thermal Plant |
Nagarjuna Construction Company |
2640 |
15,612,170 |
|
Deferred |
|
| Andhra Pradesh |
NCC Vamsadhara Mega Power Project |
Nagarjuna Construction Company |
1960 |
11,590,854 |
|
Unconfirmed |
|
| Andhra Pradesh |
Ontimavadi power station |
GMR Energy |
6300 |
37,256,315 |
|
Planning |
|
| Andhra Pradesh |
Paloncha power station expansion #1 |
Nava Bharat Ventures Ltd |
150 |
887,055 |
|
Construction |
|
| Andhra Pradesh |
Paloncha power station expansion #2 |
Nava Bharat Ventures Ltd |
150 |
887,055 |
|
Planning |
|
| Andhra Pradesh |
Pegadapalli (Jaipur Mandal) power station |
Singareni Collieries |
600 |
3,548,220 |
|
Construction |
|
| Andhra Pradesh |
Pentakota power station |
Namratha Bizili Private Limited |
150 |
887,055 |
|
Deferred |
|
| Andhra Pradesh |
Pentakota power station (Srinivasam Energy) |
Srinivasam Energy Limited |
1320 |
7,806,085 |
Supercritical |
Unconfirmed |
|
| Andhra Pradesh |
Pudimadaka Ultra Mega Power Project |
NTPC |
4000 |
23,654,803 |
Supercritical |
Advanced development |
|
| Andhra Pradesh |
Ramagundam Stage-IV |
NTPC |
1000 |
5,913,701 |
|
Early development |
|
| Andhra Pradesh |
Rayalaseema Thermal Power Project Stage-III (Unit 5) |
Andhra Pradesh Power Generation Corporation (APGENCO) |
210 |
1,241,877 |
|
Newly commissioned |
2010 |
| Andhra Pradesh |
Rayalaseema Thermal Power Project Stage-IV (Unit 6) |
Andhra Pradesh Power Generation Corporation (APGENCO) |
600 |
3,548,220 |
|
Construction |
2014 |
| Andhra Pradesh |
Saggonda power station |
Andhra Sugars |
120 |
709,644 |
|
Planning |
|
| Andhra Pradesh |
Sattupally Thermal Power Station |
Andhra Pradesh Power Generation Corporation (APGENCO) |
600 |
3,548,220 |
|
Early development |
|
| Andhra Pradesh |
Sigma Infrarop power station (Khamman) |
Sigma Infrarop Ltd |
2640 |
15,612,170 |
|
Unconfirmed |
|
| Andhra Pradesh |
Simhadri power station units 3 and 4 |
NTPC |
1000 |
5,913,701 |
|
Newly commissioned |
2011, 2012 |
| Andhra Pradesh |
Sompeta power station (Suryachakra) |
Suryachakra Group |
1200 |
7,096,441 |
|
Unconfirmed |
|
| Andhra Pradesh |
Sree Siva Satyadeva Power Plant |
Sree Siva Satyadeva Power Plant Pvt. |
2000 |
11,827,402 |
|
Cancelled |
|
| Andhra Pradesh |
Sri Damodaram Sanjeevaiah (Krishnapatnam) Thermal Power Station |
Andhra Pradesh Power Generation Corporation (APGENCO) |
1600 |
9,461,921 |
|
Construction |
2012 |
| Andhra Pradesh |
Srikakulam Thermal Power Station |
Andhra Pradesh Power Generation Corporation (APGENCO) |
2400 |
14,192,882 |
|
Early development |
|
| Andhra Pradesh |
Thamminapatnam power station (Simhapuri) Phase I Unit 1 |
Simhapuri Energy |
150 |
887,055 |
Subcritical |
Newly commissioned |
2012 |
| Andhra Pradesh |
Thamminapatnam power station (Simhapuri) Phase I Unit 2 |
Simhapuri Energy |
150 |
887,055 |
Subcritical |
Newly commissioned |
2012 |
| Andhra Pradesh |
Thamminapatnam power station (Simhapuri) Phase-II |
Simhapuri Energy |
300 |
1,774,110 |
Subcritical |
Construction |
2012 |
| Andhra Pradesh |
Thamminapatnam power station (Simhapuri) Phase-III |
Simhapuri Energy |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2013 |
| Andhra Pradesh |
Uppada power station |
Spectrum Power Generation |
1320 |
7,806,085 |
|
Cancelled |
|
| Andhra Pradesh |
Vadarevu Ultra Mega Power Project Stages II-III |
Andhra Pradesh Power Generation Corporation (APGENCO) |
2400 |
14,192,882 |
|
Planning |
|
| Andhra Pradesh |
Varadevu Ultra Mega Power Project Stage I |
Andhra Pradesh Power Generation Corporation (APGENCO) |
1600 |
9,461,921 |
|
Early development |
|
| Andhra Pradesh |
VBF Ferro Alloys Bodepalli plant |
VBC Ferro Alloys |
120 |
709,644 |
|
Planning |
|
| Andhra Pradesh |
Vijayawada Thermal Power Station (IGCC) |
Andhra Pradesh Power Generation Corporation (APGENCO) |
182 |
1,076,294 |
IGCC |
Early development |
2014 |
| Andhra Pradesh |
Vijayawada Thermal Power Station expansion |
Andhra Pradesh Power Generation Corporation (APGENCO) |
800 |
4,730,961 |
|
Planning |
|
| Andhra Pradesh |
Vikas Power thermal plant |
Vikas Power |
540 |
3,193,398 |
|
Planning |
|
| Andhra Pradesh |
Vizag Thermal Power Plant |
Hinduja National Power Corporation |
1040 |
6,150,249 |
|
Construction |
2013 |
| Andhra Pradesh |
Welspun Andhra Pradesh project |
Welspun Energy |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Assam |
Bongaigaon power station Stage I |
NTPC |
750 |
4,435,276 |
|
Construction |
|
| Assam |
Bongaigaon power station Stage II |
NTPC |
250 |
1,478,425 |
|
Planning |
|
| Assam |
Borgolai power station |
Assam Power Projects Development Company Ltd |
250 |
1,478,425 |
|
Planning |
|
| Assam |
Margherita power station |
NEEPCO and APGCL |
480 |
2,838,576 |
|
Planning |
|
| Assam |
Naitor power station |
Globe Power & Steel |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| Bihar |
Banka Power Project |
Abhijeet Group |
3960 |
23,418,255 |
Supercritical |
Uncertain |
2014 |
| Bihar |
Barauni power station expansion |
Bihar State Electricity Board |
500 |
2,956,850 |
|
Early development |
2014 |
| Bihar |
Barh I power station |
NTPC |
1980 |
11,709,128 |
|
Construction |
|
| Bihar |
Barh II power station |
NTPC |
1320 |
7,806,085 |
Supercritical |
Construction |
|
| Bihar |
Bhagalpur Power Project |
Ganga Power & Natural Resources |
2640 |
15,612,170 |
|
Early development |
|
| Bihar |
Buxar Thermal Power Station (Chausa) |
Buxar Bijlee Company |
1320 |
7,806,085 |
|
Early development |
2016 |
| Bihar |
Indragacchi power station |
India Power Corporation |
1320 |
7,806,085 |
Supercritical |
Early development |
2015 |
| Bihar |
Jagdishpur power station Stage 1 |
AES India |
1320 |
7,806,085 |
|
Early development |
2016 |
| Bihar |
Jagdishpur power station Stage 2 |
AES India |
1320 |
7,806,085 |
|
Planning |
|
| Bihar |
Kahalgaon power station (Cement Manufacturing Co.) |
Cement Manufacturing Company Ltd. |
500 |
2,956,850 |
|
Cancelled |
|
| Bihar |
Kahalgaon power station (East-West Power) |
East-West Power Generation Co. Ltd. |
1000 |
5,913,701 |
|
Cancelled |
|
| Bihar |
Kahalgaon power station (Sarvottam) |
Sarvottam Infrastructure |
540 |
3,193,398 |
|
Cancelled |
|
| Bihar |
Kahalgaon Super Thermal Power Plant St-III Extension |
NTPC |
500 |
2,956,850 |
|
Planning |
|
| Bihar |
Kiul Thermal Power Project (Lakhisarai) |
Mirach Power Pvt. Ltd |
1320 |
7,806,085 |
|
Planning |
|
| Bihar |
Kochar power station |
Triton Energy Ltd. |
1320 |
7,806,085 |
|
Planning |
|
| Bihar |
Lakhisarai power station (SPML) |
SPML |
1200 |
7,096,441 |
|
Planning |
|
| Bihar |
Lakhisarai Thermal Power Station (Kajara) |
Lakhisarai Bijlee |
1320 |
7,806,085 |
|
Advanced development |
2016 |
| Bihar |
Meherpur power station |
Usha Martin |
1200 |
7,096,441 |
|
Uncertain |
|
| Bihar |
Muzaffarpur power station extension |
Bihar State Electricity Board |
390 |
2,306,343 |
|
Construction |
2013 |
| Bihar |
Nabinagar (Majhiyan) Super Thermal Power Project |
Nabinagar Power Generating Company |
1980 |
11,709,128 |
Supercritical |
Advanced development |
2016 |
| Bihar |
Nabinagar Thermal Power Project |
NTPC and Ministry of Railways |
1000 |
5,913,701 |
|
Construction |
|
| Bihar |
Pirpainti power station (CESC) |
CESC |
2000 |
11,827,402 |
|
Early development |
2017 |
| Bihar |
Pirpainti power station (Essar) |
Essar Energy |
1800 |
10,644,661 |
|
Deferred |
|
| Bihar |
Pirpainti Thermal Power Station |
Pirpainti Bijlee Company |
1320 |
7,806,085 |
|
Early development |
2016 |
| Bihar |
Prabhawati Nagar power station |
Arrissan Power Limited |
1320 |
7,806,085 |
|
Early development |
|
| Bihar |
Sirdala power station |
Global Powmin |
2640 |
15,612,170 |
|
Early development |
2014 |
| Chhattisgarh |
Akaltara Ultra Mega Power Project |
Akaltara Power |
4000 |
23,654,803 |
|
Cancelled |
|
| Chhattisgarh |
Amarkantak Thermal Power Project phase I (Pathadi) unit 2 |
Lanco |
300 |
1,774,110 |
|
Newly commissioned |
2010 |
| Chhattisgarh |
Amarkantak Thermal Power Project phase II (Pathadi) units 3 and 4 |
Lanco |
1320 |
7,806,085 |
Supercritical |
Construction |
2013, 2014 |
| Chhattisgarh |
Amoda power station |
DCM Shriram Consolidated |
600 |
3,548,220 |
|
Early development |
|
| Chhattisgarh |
Arasmeta Expansion Power Plant |
KSK Energy Ventures |
43 |
254,289 |
|
Construction |
|
| Chhattisgarh |
Athena Chhattisgarh power station |
Athena Chhattisgarh Power Limited |
1200 |
7,096,441 |
|
Construction |
2014 |
| Chhattisgarh |
Avantha Bhandar power station Unit 1 |
Avantha Power and Infrastructure |
600 |
3,548,220 |
|
Construction |
2013 |
| Chhattisgarh |
Avantha Bhandar power station Unit 2 |
Avantha Power and Infrastructure |
600 |
3,548,220 |
|
Early development |
|
| Chhattisgarh |
BALCO Korba power station expansion |
Bharat Aluminium Company |
600 |
3,548,220 |
|
Construction |
2013-2014 |
| Chhattisgarh |
BALCO Korba power station expansion |
Bharat Aluminium Company |
600 |
3,548,220 |
|
Construction |
|
| Chhattisgarh |
Balpur power station |
Jain Energy |
1200 |
7,096,441 |
|
Early development |
|
| Chhattisgarh |
Baradarha power station |
DB Power |
1200 |
7,096,441 |
|
Construction |
2013 |
| Chhattisgarh |
Bhaiso power station (Janjgir-Champa) Phase 1 |
KVK Power & Infrastructure Pvt. Ltd. |
600 |
3,548,220 |
|
Early development |
|
| Chhattisgarh |
Bhaiso power station (Janjgir-Champa) Phase 2 |
KVK Power & Infrastructure Pvt. Ltd. |
600 |
3,548,220 |
|
Planning |
|
| Chhattisgarh |
Bhaiyathan Thermal Power Project |
Indiabulls Power and Chhattisgarh State Power Generation Company |
1320 |
7,806,085 |
|
Early development |
2013 |
| Chhattisgarh |
Bhandhakhar power station |
Maruti Clean Coal and Power |
300 |
1,774,110 |
|
Construction |
2013 |
| Chhattisgarh |
Bhengari power station |
Mahavir Global Coal Limited (MGCL) |
540 |
3,193,398 |
|
Planning |
|
| Chhattisgarh |
Bhushan Steel Chhattisgarh project |
Bhushan Steel |
1000 |
5,913,701 |
|
Planning |
|
| Chhattisgarh |
Birra Thermal Power Project |
Moser Baer Power & Infrastructures |
1320 |
7,806,085 |
|
Early development |
|
| Chhattisgarh |
BLA Chhattisgarh power station |
BLA Power |
540 |
3,193,398 |
|
Cancelled |
|
| Chhattisgarh |
Bunji Bundeli Thermal Power Project |
Chhattisgarh State Power Generation Company |
500 |
2,956,850 |
|
Early development |
|
| Chhattisgarh |
Chakabura power station expansion unit 1 |
ACB (India) |
135 |
798,350 |
Subcritical |
Newly commissioned |
2011 |
| Chhattisgarh |
Chakabura power station expansion unit 2 |
ACB (India) |
135 |
798,350 |
Subcritical |
Construction |
2012 |
| Chhattisgarh |
Champa Adhunik power station |
Adhunik Power and Natural Resources |
1320 |
7,806,085 |
|
Planning |
|
| Chhattisgarh |
Champa Power Project |
ACB (India) |
1200 |
7,096,441 |
|
Early development |
|
| Chhattisgarh |
Chandan Nagar power station |
IFFCO Chhattisgarh Power |
1000 |
5,913,701 |
|
Planning |
|
| Chhattisgarh |
Chhattisgarh GMR power station Phase I |
GMR Energy |
1370 |
8,101,770 |
|
Advanced development |
2014 |
| Chhattisgarh |
Chhattisgarh GMR power station Phase II |
GMR Energy |
685 |
4,050,885 |
|
Early development |
2015 |
| Chhattisgarh |
Dhardai power station |
JSW ISPAT Steel |
1200 |
7,096,441 |
|
Unconfirmed |
|
| Chhattisgarh |
Facor Power Chhattisgarh power project |
Facor Power |
600 |
3,548,220 |
Supercritical |
Early development |
|
| Chhattisgarh |
Godhna power station |
Karnataka Power Corporation |
1600 |
9,461,921 |
|
Planning |
|
| Chhattisgarh |
Gorra Thermal Power Plant |
Patni Power Projects |
540 |
3,193,398 |
|
Planning |
|
| Chhattisgarh |
IFFCO-CSPGCL Thermal Power Project |
Chhattisgarh State Power Generation Company |
1320 |
7,806,085 |
|
Early development |
|
| Chhattisgarh |
Janjgir power station |
Karnataka Power Corporation |
1200 |
7,096,441 |
|
Planning |
2013 |
| Chhattisgarh |
Kasaipalli power station |
Aryan Coal Benefications |
270 |
1,596,699 |
|
Newly commissioned |
2011-2012 |
| Chhattisgarh |
Khamhar power station |
AES Chhattisgarh Energy |
1440 |
8,515,729 |
|
Planning |
|
| Chhattisgarh |
Korba III power station |
NTPC |
500 |
2,956,850 |
|
Newly commissioned |
2010 |
| Chhattisgarh |
Korba South Thermal Power Project Unit 1 and Unit 2 |
Chhattisgarh State Power Generation Company |
1000 |
5,913,701 |
|
Early development |
2014 |
| Chhattisgarh |
Korba West (Hasdeo Thermal Power Station) Extension |
Chhattisgarh State Power Generation Company |
500 |
2,956,850 |
|
Construction |
2013 |
| Chhattisgarh |
KSK Mahanadi Power Project Units 1-4 |
KSK Energy Ventures |
2400 |
14,192,882 |
|
Construction |
2013, 2014 |
| Chhattisgarh |
KSK Mahanadi Power Project Units 5-6 |
KSK Energy Ventures |
1200 |
7,096,441 |
|
Planning |
|
| Chhattisgarh |
KSK Narmada Power Project |
KSK Energy Ventures |
1800 |
10,644,661 |
|
Early development |
|
| Chhattisgarh |
Kukurda power station |
JSW Energy |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Chhattisgarh |
Kukurda power station |
JSW Energy |
1320 |
7,806,085 |
Supercritical |
Advanced development |
|
| Chhattisgarh |
Lanco Chhattisgarh Thermal Power Project |
Lanco |
2000 |
11,827,402 |
|
Planning |
|
| Chhattisgarh |
Lara Integrated Thermal Power Project 1-2 |
NTPC |
1600 |
9,461,921 |
Supercritical |
Advanced development |
2014 |
| Chhattisgarh |
Lara Integrated Thermal Power Project 3-4 |
NTPC |
1600 |
9,461,921 |
Supercritical |
Planning |
2015 |
| Chhattisgarh |
Lara Integrated Thermal Power Project 5 |
NTPC |
800 |
4,730,961 |
Supercritical |
Planning |
2016 |
| Chhattisgarh |
Marwa power station |
Chhattisgarh State Power Generation Company |
1000 |
5,913,701 |
|
Construction |
2013 |
| Chhattisgarh |
Moser Baer Captive Power Project |
Moser Baer Power & Infrastructures and PTC India |
150 |
887,055 |
|
Early development |
|
| Chhattisgarh |
Pathadi power station |
Lanco and KVK |
1320 |
7,806,085 |
|
Construction |
|
| Chhattisgarh |
Raigarh Power Project (TRN/ACB) |
ACB (India) |
600 |
3,548,220 |
|
Construction |
2014 |
| Chhattisgarh |
Raigarh power station (SKS Ispat) |
SKS Ispat and Power |
1200 |
7,096,441 |
|
Construction |
2014-2015 |
| Chhattisgarh |
Raigarh Project (Jindal) |
Jindal Power |
1320 |
7,806,085 |
Supercritical |
Advanced development |
|
| Chhattisgarh |
Raigarh project (VISA Power) |
VISA Power |
1200 |
7,096,441 |
|
Advanced development |
2013 |
| Chhattisgarh |
Raikheda power station |
GMR Energy |
1370 |
8,101,770 |
Supercritical |
Construction |
2014 |
| Chhattisgarh |
Ratija Power Project Phase I |
ACB (India) |
50 |
295,685 |
Subcritical |
Construction |
2012 |
| Chhattisgarh |
Ratija Power Project Phase II |
ACB (India) |
50 |
295,685 |
Subcritical |
Early development |
|
| Chhattisgarh |
Sapnai power station |
Topworth Energy |
1260 |
7,451,263 |
|
Early development |
|
| Chhattisgarh |
Sapos power station (BEC Power) |
BEC Power |
500 |
2,956,850 |
|
Early development |
|
| Chhattisgarh |
Sapos power station (Suryachakra) |
Suryachakra Group |
1320 |
7,806,085 |
Ultra Supercritical |
Advanced development |
|
| Chhattisgarh |
Sipat I power station expansion, units 1, 2, and 3 |
NTPC |
1980 |
11,709,128 |
Supercritical |
Newly commissioned |
2011, 2012 |
| Chhattisgarh |
Surguja Ultra Mega Power Project |
not selected |
4000 |
23,654,803 |
|
Uncertain |
|
| Chhattisgarh |
SV Power project (Renki) phase II |
KVK |
300 |
1,774,110 |
|
Early development |
|
| Chhattisgarh |
Tamnar II Project |
Jindal Power |
2400 |
14,192,882 |
Subcritical |
Construction |
2014-2015 |
| Chhattisgarh |
Uchpinda power station |
RKM Powergen Private Limited |
1440 |
8,515,729 |
|
Construction |
2013-2014 |
| Gujarat |
Akrimota Power Project expansion |
Gujarat Mineral Development Corporation |
250 |
1,478,425 |
|
Unconfirmed |
|
| Gujarat |
Amreli power station |
Avantha Power and Infrastructure |
1320 |
7,806,085 |
Supercritical |
Planning |
2016 |
| Gujarat |
Bhadreshwar power station (OPG) |
OPG Power Ventures |
300 |
1,774,110 |
|
Deferred |
|
| Gujarat |
Bhadreshwar Thermal Power Project (Adani) |
Adani Power |
3300 |
19,515,213 |
|
Planning |
|
| Gujarat |
Bharuch DCM power station |
DCM Shriram Consolidated |
48 |
283,858 |
|
Planning |
|
| Gujarat |
Bhavnagar power station |
Gujarat Power Corporation |
500 |
2,956,850 |
|
Construction |
2013 |
| Gujarat |
Bherai power station |
VISA Power |
1320 |
7,806,085 |
|
Early development |
|
| Gujarat |
Dahej power station (JSW Energy) |
JSW Energy |
2400 |
14,192,882 |
|
Planning |
|
| Gujarat |
Dahej Thermal Power Project |
Adani Power |
2640 |
15,612,170 |
|
Deferred |
|
| Gujarat |
Dholera Power Plant |
Gujarat State Electricity Corp |
1600 |
9,461,921 |
|
Planning |
2018 |
| Gujarat |
Dhuvaran Super Thermal Power Project |
NTPC |
1320 |
7,806,085 |
|
Planning |
|
| Gujarat |
Gujarat Power Project (Valia) |
Neyveli Lignite Corporation |
500 |
2,956,850 |
|
Planning |
|
| Gujarat |
Hazira II power plant |
Essar Energy |
270 |
1,596,699 |
|
Construction |
|
| Gujarat |
Jamnagar Complex power station |
Reliance Industries |
1000 |
5,913,701 |
|
Planning |
|
| Gujarat |
Mundra Thermal Power Project (Adani) Phase I Units 1-9 |
Adani Power |
4620 |
27,321,298 |
Subcritical |
Newly commissioned |
2009-2012 |
| Gujarat |
Okha power station |
SPR Infrastructure India |
2640 |
15,612,170 |
Supercritical |
Early development |
|
| Gujarat |
Pipavav power station |
Torrent Power and Gujarat Power Corporation |
2000 |
11,827,402 |
|
Early development |
|
| Gujarat |
Salaya I power plant |
Essar Energy |
1200 |
7,096,441 |
Subcritical |
Newly commissioned |
2012 |
| Gujarat |
Salaya II power plant |
Essar Energy |
1320 |
7,806,085 |
Supercritical |
Construction |
|
| Gujarat |
Salaya III power plant |
Essar Energy |
600 |
3,548,220 |
Circulating Fluidized Bed |
Construction |
|
| Gujarat |
Sikka Thermal Power Station Units 3-4 |
Gujarat State Electricity Corp |
500 |
2,956,850 |
|
Construction |
2013 |
| Gujarat |
Simar power station |
JSW Energy |
1600 |
9,461,921 |
|
Cancelled |
|
| Gujarat |
Surat Lignite Ext Units 3-4 |
Gujarat Industries |
250 |
1,478,425 |
|
Newly commissioned |
2011 |
| Gujarat |
Suryachakra captive power plant |
Suryachakra Group |
200 |
1,182,740 |
|
Early development |
|
| Gujarat |
Tata Mundra Ultra Mega Power Project 1-2 |
Tata Power |
1600 |
9,461,921 |
Supercritical |
Newly commissioned |
2011-2012 |
| Gujarat |
Tata Mundra Ultra Mega Power Project 3-5 |
Tata Power |
2400 |
14,192,882 |
Supercritical |
Construction |
2013 |
| Gujarat |
Ukai Thermal Power Station Unit 6 |
Gujarat State Electricity Corp |
500 |
2,956,850 |
|
Construction |
2013 |
| Gujarat |
Wanakbori Thermal Power Station Unit 8 |
Gujarat State Electricity Corp |
800 |
4,730,961 |
|
Early development |
2016 |
| Haryana |
Deenbandhu Chhotu Ram Thermal Power Plant expansion |
Haryana Power Generation Company |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Haryana |
Indira Gandhi Super Thermal Power Project Unit 3 |
NTPC |
500 |
2,956,850 |
Subcritical |
Construction |
2012 |
| Haryana |
Indira Gandhi Super Thermal Power Project Units 1-2 |
NTPC |
1000 |
5,913,701 |
Subcritical |
Newly commissioned |
2011 |
| Haryana |
Jhajjar power station |
CLP India |
1320 |
7,806,085 |
Supercritical |
Newly commissioned |
2012 |
| Haryana |
Mahatma Gandhi Thermal Power Project Units 1 and 2 |
Haryana Power Generation Company |
1320 |
7,806,085 |
|
Newly commissioned |
2012 |
| Haryana |
Rajiv Gandhi Thermal Power Project Hisar Unit I |
Haryana Power Generation Company |
600 |
3,548,220 |
|
Newly commissioned |
2010 |
| Haryana |
Rajiv Gandhi Thermal Power Project Hisar Unit II |
Haryana Power Generation Company |
600 |
3,548,220 |
|
Newly commissioned |
2011 |
| Jharkhand |
Baranda power station |
JSW Energy |
1620 |
9,580,195 |
|
Early development |
|
| Jharkhand |
Bhagalpur power station |
Gagan Power & Natural Resources |
1320 |
7,806,085 |
|
Early development |
|
| Jharkhand |
Bokaro A Thermal Power Station |
Damodar Valley Corporation |
500 |
2,956,850 |
|
Construction |
2014 |
| Jharkhand |
Bokaro Steel City Thermal Power Station expansion |
Damodar Valley Corporation |
500 |
2,956,850 |
|
Planning |
|
| Jharkhand |
Chandil Singh power station |
HDIL Energy |
1320 |
7,806,085 |
Supercritical |
Unconfirmed |
|
| Jharkhand |
Chandrapura power station |
Damodar Valley Corporation |
500 |
2,956,850 |
|
Newly commissioned |
2011 |
| Jharkhand |
Chandwa Power Project Phase I |
Abhijeet Group |
1080 |
6,386,797 |
Subcritical |
Construction |
2013 |
| Jharkhand |
Chandwa Power Project Phase II |
Abhijeet Group |
675 |
3,991,748 |
|
Early development |
|
| Jharkhand |
Chandwa Power Project Phase III |
Abhijeet Group |
660 |
3,903,043 |
|
Early development |
|
| Jharkhand |
Chichro Patsimal power station |
NTPC & Coal India |
2000 |
11,827,402 |
|
Cancelled |
|
| Jharkhand |
Dumka power station (CESC) Phase I |
CESC |
600 |
3,548,220 |
|
Early development |
2016 |
| Jharkhand |
Dumka power station (CESC) Phase I |
CESC |
660 |
3,903,043 |
|
Planning |
|
| Jharkhand |
Dumka Project |
Jindal Power |
1300 |
7,687,811 |
Supercritical |
Early development |
2014 |
| Jharkhand |
Godda Project |
Jindal Power |
660 |
3,903,043 |
Supercritical |
Advanced development |
|
| Jharkhand |
Gumla power station (Kamdara) |
Jharkhand State Electricity Board |
1320 |
7,806,085 |
|
Early development |
|
| Jharkhand |
Mahadev Prasad Super Thermal Power Station stage I |
Adhunik Power and Natural Resources |
270 |
1,596,699 |
Subcritical |
Newly commissioned |
2012 |
| Jharkhand |
Mahadev Prasad Super Thermal Power Station stage II |
Adhunik Power and Natural Resources |
270 |
1,596,699 |
|
Construction |
2013 |
| Jharkhand |
Mahadev Prasad Super Thermal Power Station stage III |
Adhunik Power and Natural Resources |
540 |
3,193,398 |
|
Planning |
|
| Jharkhand |
Jharkhand Aluminium power station |
Hindalco Industries |
900 |
5,322,331 |
|
Early development |
|
| Jharkhand |
Jharkhand Project |
Jindal Power |
2640 |
15,612,170 |
Supercritical |
Planning |
|
| Jharkhand |
Jojobera Power Plant unit 5 |
Tata Power |
120 |
709,644 |
|
Newly commissioned |
2011 |
| Jharkhand |
Kamdara power station |
Jharkhand State Electricity Board |
1320 |
7,806,085 |
|
Construction |
|
| Jharkhand |
Koderma Thermal Power Station Unit 1 |
Damodar Valley Corporation |
500 |
2,956,850 |
|
Newly commissioned |
2011 |
| Jharkhand |
Koderma Thermal Power Station Unit 2 |
Damodar Valley Corporation |
500 |
2,956,850 |
|
Construction |
2012 |
| Jharkhand |
KVK Jharkhand project |
KVK Nilachal Power Pvt. Ltd. |
1000 |
5,913,701 |
|
Early development |
|
| Jharkhand |
Maithon Right Bank Thermal Power Station |
Damodar Valley Corporation and Tata Power |
1050 |
6,209,386 |
Subcritical |
Newly commissioned |
2011-2012 |
| Jharkhand |
Maithon Right Bank Thermal Power Station Phase II |
Damodar Valley Corporation and Tata Power |
1600 |
9,461,921 |
Subcritical |
Early development |
|
| Jharkhand |
Malaxmi Mega Thermal Power Project (Thakurbari) |
Malaxmi |
2640 |
15,612,170 |
|
Unconfirmed |
|
| Jharkhand |
Patratu power station (Jinbhuvish Energy) |
Jinbhuvish Energy (East) |
1320 |
7,806,085 |
|
Planning |
|
| Jharkhand |
Rahem power station |
Gupta Energy |
1000 |
5,913,701 |
|
Unconfirmed |
|
| Jharkhand |
Sahibganj power station |
Madhucon Projects |
1320 |
7,806,085 |
|
Early development |
|
| Jharkhand |
Saraikela power station |
Kohinoor Power |
215 |
1,271,446 |
|
Construction |
|
| Jharkhand |
Tilaiya Ultra Mega Power Project 1-5 |
Reliance Power |
3300 |
19,515,213 |
Supercritical |
Early development |
2015 |
| Jharkhand |
Tilaiya Ultra Mega Power Project 6 |
Reliance Power |
660 |
3,903,043 |
Supercritical |
Early development |
2017 |
| Jharkhand |
Tiruldih Power Project |
Tata Power |
1980 |
11,709,128 |
|
Early development |
|
| Jharkhand |
Tori power plant |
Essar Energy |
1200 |
7,096,441 |
|
Construction |
2014 |
| Jharkhand |
Visa Power Jharkhand project |
VISA Power |
2640 |
15,612,170 |
|
Early development |
|
| Jharkhand |
Welspun Energy Parbahal Thermal Power Plant |
Welspun Energy |
1980 |
11,709,128 |
|
Early development |
|
| Karnataka |
Bellary Thermal Power Station 2 |
Karnataka Power Corporation |
500 |
2,956,850 |
|
Newly commissioned |
2012 |
| Karnataka |
Bellary Thermal Power Station 3 |
Karnataka Power Corporation |
700 |
4,139,591 |
|
Planning |
2014 |
| Karnataka |
Chamalapura power station |
Karnataka Power Corporation |
1000 |
5,913,701 |
|
Cancelled |
|
| Karnataka |
Edlapura power station |
Karnataka Power Corporation |
800 |
4,730,961 |
Supercritical |
Planning |
|
| Karnataka |
Ghataprabha power station |
Power Company of Karnataka (PCKL) |
1320 |
7,806,085 |
|
Early development |
|
| Karnataka |
Gulbarga power station |
Power Company of Karnataka (PCKL) |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Karnataka |
Hanakon Thermal Power Project |
Ind-Barath Power |
450 |
2,661,165 |
|
Cancelled |
|
| Karnataka |
Hassan power station |
Hassan Thermal Power (P) Ltd |
1000 |
5,913,701 |
|
Early development |
|
| Karnataka |
Jewargi power station |
Jewargi Power Pvt Ltd. |
1320 |
7,806,085 |
|
Planning |
|
| Karnataka |
JSW Vijayanagar power station expansion |
JSW Energy |
660 |
3,903,043 |
Supercritical |
Advanced development |
|
| Karnataka |
Kadechur power station |
Atlas Power India |
1320 |
7,806,085 |
|
Early development |
|
| Karnataka |
Karnataka Gupta power station |
Gupta Power |
1320 |
7,806,085 |
|
Unconfirmed |
|
| Karnataka |
Kudgi Super Thermal Power Project Stage I |
NTPC |
2400 |
14,192,882 |
Supercritical |
Construction |
2015-2016 |
| Karnataka |
Kudgi Super Thermal Power Project Stage II |
NTPC |
1600 |
9,461,921 |
Supercritical |
Early development |
|
| Karnataka |
Mangoli power station |
Flamingo Energy Ventures |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Karnataka |
Mulwad power station |
Luxor Energy |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Karnataka |
Raichur Thermal Power Station expansion |
Karnataka Power Corporation |
250 |
1,478,425 |
Subcritical |
Newly commissioned |
2010 |
| Karnataka |
Tadri Ultra Mega Power Project |
NTPC |
4000 |
23,654,803 |
|
Deferred |
|
| Karnataka |
Udupi Power unit 1 |
Lanco |
600 |
3,548,220 |
Subcritical |
Newly commissioned |
2010 |
| Karnataka |
Udupi Power unit 2 |
Lanco |
600 |
3,548,220 |
Subcritical |
Newly commissioned |
2011 |
| Karnataka |
Udupi Power units 3 & 4 |
Lanco |
1320 |
7,806,085 |
|
Early development |
|
| Karnataka |
Vadlur power station |
Surana Power Ltd |
420 |
2,483,754 |
|
Advanced development |
2013 |
| Karnataka |
Vantamuri power station |
Shree Renuka Energy |
1050 |
6,209,386 |
|
Early development |
|
| Karnataka |
Yedlapur thermal station |
Karnataka Power Corporation |
850 |
5,026,646 |
Supercritical |
Advanced development |
2014 |
| Karnataka |
Yeramarus thermal station |
Karnataka Power Corporation |
850 |
5,026,646 |
Supercritical |
Advanced development |
2014 |
| Kerala |
Kasargod power station |
Kerala State Industrial Development Corp. |
2520 |
14,902,526 |
Supercritical |
Early development |
|
| Madhya Pradesh |
Anuppur power station (Newzone) |
New Zone India |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Madhya Pradesh |
Anuppur Thermal Power Project Phase 1 |
Moser Baer Power & Infrastructures |
1200 |
7,096,441 |
Subcritical |
Construction |
|
| Madhya Pradesh |
Anuppur Thermal Power Project Phase 2 |
Moser Baer Power & Infrastructures |
1320 |
7,806,085 |
|
Early development |
|
| Madhya Pradesh |
Banas Thermal Power project (Anuppur) |
KVK Power & Infrastructure Pvt. Ltd. |
1320 |
7,806,085 |
|
Planning |
|
| Madhya Pradesh |
Bansagar power station |
MPTradco |
1600 |
9,461,921 |
Supercritical |
Early development |
2015 |
| Madhya Pradesh |
Barethi Super Thermal Power Project |
NTPC |
3960 |
23,418,255 |
Supercritical |
Early development |
|
| Madhya Pradesh |
Bina Refinery power station |
Bharat Oman Refinery |
99 |
585,456 |
|
Construction |
|
| Madhya Pradesh |
Bina Thermal Power Project additional units |
Jaiprakash Power Ventures |
750 |
4,435,276 |
|
Planning |
2012 |
| Madhya Pradesh |
Bina Thermal Power Project Unit 1 |
Jaiprakash Power Ventures |
250 |
1,478,425 |
|
Newly commissioned |
2012 |
| Madhya Pradesh |
Bina Thermal Power Project Unit 2 |
Jaiprakash Power Ventures |
250 |
1,478,425 |
|
Construction |
2013 |
| Madhya Pradesh |
Chhindwara JSW power station |
JSW Energy |
1320 |
7,806,085 |
Supercritical |
Cancelled |
|
| Madhya Pradesh |
Chitrangi Power Project |
Reliance Power |
3960 |
23,418,255 |
Supercritical |
Advanced development |
|
| Madhya Pradesh |
Dada Dhuniwale Thermal Power Project |
M.P. Power Generating Company |
1600 |
9,461,921 |
|
Early development |
|
| Madhya Pradesh |
Gadarwara power station (BLA) |
BLA Power |
140 |
827,918 |
Subcritical |
Advanced development |
|
| Madhya Pradesh |
Gadarwara Super Thermal Power Project |
NTPC |
1320 |
7,806,085 |
|
Early development |
|
| Madhya Pradesh |
Jabalpur Thermal Power Project |
VISA Power |
1320 |
7,806,085 |
|
Early development |
|
| Madhya Pradesh |
Jaypee Nigrie Super Thermal Power Project |
Jaiprakash Power Ventures |
1320 |
7,806,085 |
Supercritical |
Construction |
2013 |
| Madhya Pradesh |
Jhabua (Chetak) power station |
Chetak Enterprises |
1320 |
7,806,085 |
|
Deferred |
|
| Madhya Pradesh |
Jhabua Power Seoni power station phase 1 |
Avantha Power and Infrastructure |
600 |
3,548,220 |
Subcritical |
Construction |
2014 |
| Madhya Pradesh |
Jhabua Power Seoni power station phase 2 |
Avantha Power and Infrastructure |
600 |
3,548,220 |
Subcritical |
Advanced development |
|
| Madhya Pradesh |
Katni power station |
Welspun Energy |
1980 |
11,709,128 |
Supercritical |
Advanced development |
|
| Madhya Pradesh |
Khargaone power station |
NTPC |
0 |
0 |
|
Planning |
|
| Madhya Pradesh |
Madhya Pradesh Jain Energy power station (Birhulee) |
Jain Energy |
1320 |
7,806,085 |
|
Early development |
|
| Madhya Pradesh |
Mahan Aluminium power station |
Hindalco Industries |
900 |
5,322,331 |
|
Construction |
|
| Madhya Pradesh |
Mahan I power plant |
Essar Energy |
1200 |
7,096,441 |
Subcritical |
Construction |
2012-2013 |
| Madhya Pradesh |
Mahan II power plant |
Essar Energy |
600 |
3,548,220 |
|
Planning |
|
| Madhya Pradesh |
Maharjapur power station |
Sudama Mahavir Power |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Madhya Pradesh |
Mandsaur power station |
Chetak Enterprises |
1320 |
7,806,085 |
|
Deferred |
|
| Madhya Pradesh |
Pench Thermal Power Project |
Adani Power |
1320 |
7,806,085 |
Supercritical |
Deferred |
|
| Madhya Pradesh |
Sasan Ultra Mega Power Project 1 |
Reliance Power |
660 |
7,806,085 |
Supercritical |
Newly commissioned |
2013 |
| Madhya Pradesh |
Sasan Ultra Mega Power Project 2 |
Reliance Power |
660 |
7,806,085 |
Supercritical |
Construction |
2013 |
| Madhya Pradesh |
Sasan Ultra Mega Power Project 3 |
Reliance Power |
660 |
3,903,043 |
Supercritical |
Construction |
2014 |
| Madhya Pradesh |
Sasan Ultra Mega Power Project 4-5 |
Reliance Power |
1320 |
7,806,085 |
Supercritical |
Construction |
2015 |
| Madhya Pradesh |
Sasan Ultra Mega Power Project 6 |
Reliance Power |
660 |
3,903,043 |
Supercritical |
Construction |
2016 |
| Madhya Pradesh |
Satpura Thermal Power Station Units 10-11 |
M.P. Power Generating Company |
500 |
2,956,850 |
|
Construction |
2013 |
| Madhya Pradesh |
Shahdol power station (formerly SJK Powergen) |
GMR Energy |
1370 |
8,101,770 |
|
Early development |
2014 |
| Madhya Pradesh |
Shahpura power station |
MP Power Trading Company Limited |
1500 |
8,870,551 |
|
Early development |
|
| Madhya Pradesh |
Shree Singaji Thermal Power Project Stage I Unit 1 |
M.P. Power Generating Company |
600 |
3,548,220 |
|
Construction |
2013 |
| Madhya Pradesh |
Shree Singaji Thermal Power Project Stage I Unit 2 |
M.P. Power Generating Company |
600 |
3,548,220 |
|
Construction |
2013 |
| Madhya Pradesh |
Shree Singaji Thermal Power Project Stage II |
M.P. Power Generating Company |
1320 |
7,806,085 |
|
Planning |
|
| Madhya Pradesh |
Sidhi Power Project |
ACB (India) |
1200 |
7,096,441 |
|
Advanced development |
2014 |
| Madhya Pradesh |
Suryachakra Thermal (Madhya Pradesh) |
Suryachakra Group |
1320 |
7,806,085 |
Supercritical |
Deferred |
|
| Madhya Pradesh |
Vindhyachal-IV power station unit 11 |
NTPC |
500 |
2,956,850 |
|
Newly commissioned |
2012 |
| Madhya Pradesh |
Vindhyachal-IV power station unit 12 |
NTPC |
500 |
2,956,850 |
|
Construction |
2013 |
| Madhya Pradesh |
Vindhyachal-V power station |
NTPC |
500 |
2,956,850 |
|
Planning |
|
| Madhya Pradesh |
Welspun Amla power station |
Welspun Energy |
1320 |
7,806,085 |
|
Early development |
|
| Madhya Pradesh |
Welspun Energy Anuppur Thermal Power Plant |
Welspun Energy |
1980 |
11,709,128 |
|
Early development |
|
| Madhya Pradesh |
Welspun Mega Industrial & Energy Park |
Welspun Energy Park Pvt. Ltd. |
5280 |
31,224,340 |
|
Early development |
|
| Maharashtra |
Amravati Thermal Power Project Phase I |
Indiabulls Power |
1350 |
7,983,496 |
|
Construction |
2013-2014 |
| Maharashtra |
Amravati Thermal Power Project Phase II |
Indiabulls Power |
1350 |
7,983,496 |
|
Construction |
2014-2015 |
| Maharashtra |
Bela power station |
Ideal Energy Projects |
270 |
1,596,699 |
|
Construction |
2012 |
| Maharashtra |
Bela power station (Mantri Power) |
Mantri Power |
540 |
3,193,398 |
|
Unconfirmed |
|
| Maharashtra |
Bhadravati power station (Ispat) |
JSW ISPAT Steel |
2000 |
11,827,402 |
|
Planning |
|
| Maharashtra |
Bhadravati power station (MIDC) |
Maharashtra Industrial Development Corporation |
1320 |
7,806,085 |
|
Early development |
|
| Maharashtra |
Bhandewadi power station |
Nagpur Municipal Corporation |
500 |
2,956,850 |
|
Deferred |
|
| Maharashtra |
Bhusawal Thermal Power Station Unit 6 |
Maharashtra State Power Generation Company |
660 |
3,903,043 |
|
Advanced development |
|
| Maharashtra |
Bhusawal Thermal Power Station Units 4-5 |
Maharashtra State Power Generation Company |
1000 |
5,913,701 |
|
Newly commissioned |
2011 |
| Maharashtra |
Bijora power station |
Jinbhuvish Power Generations |
1260 |
7,451,263 |
|
Advanced development |
|
| Maharashtra |
Butibori power station |
Reliance Power |
600 |
3,548,220 |
|
Construction |
2012 |
| Maharashtra |
Chandrapur CESC power station (Tadali) |
CESC |
600 |
3,548,220 |
|
Construction |
2013 |
| Maharashtra |
Chandrapur Gupta power station stage 2 |
Gupta Energy |
540 |
3,193,398 |
|
Advanced development |
|
| Maharashtra |
Chandrapur Gupta power station stage I |
Gupta Energy |
120 |
709,644 |
|
Construction |
|
| Maharashtra |
Chandrapur Thermal Power Station unit 8 |
Maharashtra State Power Generation Company |
500 |
2,956,850 |
|
Construction |
2013 |
| Maharashtra |
Chandrapur Thermal Power Station unit 9 |
Maharashtra State Power Generation Company |
500 |
2,956,850 |
|
Construction |
2014 |
| Maharashtra |
Coastal Maharashtra Project Phase I |
Tata Power |
1600 |
9,461,921 |
Supercritical |
Deferred |
|
| Maharashtra |
Coastal Maharashtra Project Phase II |
Tata Power |
800 |
4,730,961 |
|
Deferred |
|
| Maharashtra |
Dahanu power station upgrade |
Reliance Infrastructure Limited |
1200 |
7,096,441 |
|
Uncertain |
|
| Maharashtra |
Devgad UMPP |
NTPC |
4000 |
23,654,803 |
|
Uncertain |
|
| Maharashtra |
Dhakore power station |
Ind-Barath Power |
1050 |
6,209,386 |
|
Unconfirmed |
|
| Maharashtra |
Dhariwal power station |
Haldia Energy |
600 |
3,548,220 |
|
Construction |
2013 |
| Maharashtra |
Dhopave coal plant (NTPC) |
NTPC |
1600 |
9,461,921 |
|
Planning |
|
| Maharashtra |
Dhopave Thermal Power Station (Mahagenco) Unit 1-3 |
Maharashtra State Power Generation Company |
1980 |
11,709,128 |
Supercritical |
Deferred |
|
| Maharashtra |
Dhopave Thermal Power Station (Mahagenco) Unit 4 |
Maharashtra State Power Generation Company |
800 |
4,730,961 |
Supercritical |
Cancelled |
|
| Maharashtra |
Dondaicha Thermal Power Station Stage I (Units 1 and 2) |
Maharashtra State Power Generation Company |
1320 |
7,806,085 |
|
Advanced development |
2016 |
| Maharashtra |
Dondaicha Thermal Power Station Stage II (Unit 3-5) |
Maharashtra State Power Generation Company |
1980 |
11,709,128 |
|
Planning |
2017 |
| Maharashtra |
EMCO Energy Warora Power Project |
EMCO Energy |
600 |
3,548,220 |
|
Construction |
2013 |
| Maharashtra |
Ghugus power station phase I |
Gupta Coalfields & Washeries |
120 |
709,644 |
|
Advanced development |
|
| Maharashtra |
Ghugus power station phase II |
Gupta Coalfields & Washeries |
540 |
3,193,398 |
|
Planning |
|
| Maharashtra |
Girye Ultra Mega Power Project |
Coastal Maharashtra Power Ltd. |
4000 |
23,654,803 |
|
Deferred |
|
| Maharashtra |
GMR Energy coal plant |
GMR Energy |
1800 |
10,644,661 |
|
Unconfirmed |
|
| Maharashtra |
Hari Hareshwar power station (Veshvi and Bankot) |
Hari Hareshwar Power Company |
1600 |
9,461,921 |
|
Planning |
|
| Maharashtra |
Khaperkheda TPS Unit 5 |
Maharashtra State Power Generation Company |
500 |
2,956,850 |
|
Newly commissioned |
2011 |
| Maharashtra |
Khursapar power station |
Lenexis Energy |
1320 |
7,806,085 |
|
Early development |
|
| Maharashtra |
Khutafali (Kolura) power station |
Jinbhuvish Power Generations |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Maharashtra |
Kinebodi power station |
Nandlal Enterprises |
750 |
4,435,276 |
|
Early development |
|
| Maharashtra |
Koradi Thermal Power Station 10 |
Maharashtra State Power Generation Company |
660 |
3,903,043 |
|
Construction |
2014 |
| Maharashtra |
Koradi Thermal Power Station 8 |
Maharashtra State Power Generation Company |
660 |
3,903,043 |
|
Construction |
2014 |
| Maharashtra |
Koradi Thermal Power Station 9 |
Maharashtra State Power Generation Company |
660 |
3,903,043 |
|
Construction |
2014 |
| Maharashtra |
Lanco Vidarbha Thermal Power |
Lanco |
1320 |
7,806,085 |
Supercritical |
Construction |
2014 |
| Maharashtra |
Latur power station |
Maharashtra State Power Generation Company |
1320 |
7,806,085 |
Supercritical |
Planning |
2016 |
| Maharashtra |
Madhekar power station |
Patni Energy |
405 |
2,395,049 |
CFB |
Unconfirmed |
|
| Maharashtra |
Mauda-I STPP (Nagpur) Unit 1 |
NTPC |
500 |
2,956,850 |
|
Newly commissioned |
2012 |
| Maharashtra |
Mauda-I STPP (Nagpur) Unit 2 |
NTPC |
500 |
2,956,850 |
|
Construction |
2013 |
| Maharashtra |
Mauda-II STPP (Nagpur) |
NTPC |
1320 |
7,806,085 |
|
Early development |
|
| Maharashtra |
Mendki thermal power project |
Maharashtra State Power Generation Company |
1320 |
7,806,085 |
|
Planning |
|
| Maharashtra |
Nardana power station (Vaghode) |
Shirpur Power |
300 |
1,774,110 |
|
Advanced development |
|
| Maharashtra |
Nasik Thermal Power Project Phase I (Indiabulls) |
Indiabulls Power |
1350 |
7,983,496 |
|
Construction |
2013-2015 |
| Maharashtra |
Nasik Thermal Power Project Phase I (Indiabulls) |
Indiabulls Power |
1350 |
7,983,496 |
|
Construction |
2014-2015 |
| Maharashtra |
Nasik Thermal Power Station (Sinnar) expansion |
Maharashtra State Power Generation Company |
1320 |
7,806,085 |
Supercritical |
Early development |
2017 |
| Maharashtra |
Paras power station extension |
Maharashtra State Power Generation Company |
660 |
3,903,043 |
|
Planning |
|
| Maharashtra |
Paras power station unit 4 |
Maharashtra State Power Generation Company |
250 |
1,478,425 |
|
Newly commissioned |
2010 |
| Maharashtra |
Parli Thermal Power Station Unit 7 |
Maharashtra State Power Generation Company |
250 |
1,478,425 |
Subcritical |
Newly commissioned |
2010 |
| Maharashtra |
Parli Thermal Power Station Unit 8 |
Maharashtra State Power Generation Company |
350 |
2,069,795 |
Subcritical |
Construction |
2013 |
| Maharashtra |
Rampur coal plant |
Finolex |
1000 |
5,913,701 |
|
Planning |
|
| Maharashtra |
Ratnagiri Power Plant |
JSW Energy |
1200 |
7,096,441 |
|
Newly commissioned |
2011 |
| Maharashtra |
Ratnagiri Power Plant expansion |
JSW Energy |
3200 |
18,923,843 |
Supercritical |
Deferred |
|
| Maharashtra |
Shahpur Thermal Power Project |
Reliance Power |
1200 |
7,096,441 |
|
Cancelled |
|
| Maharashtra |
Solapur power station |
NTPC |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2016 |
| Maharashtra |
Tiroda Thermal Power Project Phase I Unit 1 |
Adani Power |
660 |
3,903,043 |
Supercritical |
Newly commissioned |
2012 |
| Maharashtra |
Tiroda Thermal Power Project Phase I Unit 2 |
Adani Power |
660 |
3,903,043 |
|
Construction |
2012 |
| Maharashtra |
Tiroda Thermal Power Project Phases II and III |
Adani Power |
1980 |
11,709,128 |
|
Construction |
2013 |
| Maharashtra |
Trombay Power Station Proposed Conversion of Unit 6 to coal |
Tata Power |
500 |
2,956,850 |
Sub-critical |
Planning |
2014 (approx) |
| Maharashtra |
Waral power station |
Ind-Barath Power |
450 |
2,661,165 |
|
Cancelled |
|
| Maharashtra |
Wardha Warora Power Plant Unit 1-2 |
KSK Energy Ventures |
270 |
1,596,699 |
|
Newly commissioned |
2010 |
| Maharashtra |
Wardha Warora Power Plant Units 3-4 |
KSK Energy Ventures |
270 |
1,596,699 |
|
Newly commissioned |
2011 |
| Maharashtra |
Welspun Maxsteel power station |
Welspun Energy |
330 |
1,951,521 |
|
Early development |
|
| Meghalaya |
Garo Hills power station |
NEEPCO |
500 |
2,956,850 |
|
Early development |
|
| Meghalaya |
West Khasi Hills power station |
NEEPCO |
240 |
1,419,288 |
|
Planning |
|
| Orissa |
Aditya Aluminium power station |
Hindalco Industries |
900 |
5,322,331 |
|
Construction |
|
| Orissa |
Angul I power station (Derang) Unit 1 |
Jindal India Thermal Power |
600 |
3,548,220 |
|
Construction |
2013 |
| Orissa |
Angul I power station (Derang) Unit 2 |
Jindal India Thermal Power |
600 |
3,548,220 |
|
Construction |
2013 |
| Orissa |
Angul I power station (Derang) Unit 3 |
Jindal India Thermal Power |
600 |
3,548,220 |
|
Planning |
|
| Orissa |
Angul II power station (Derang) |
Jindal India Thermal Power |
1320 |
7,806,085 |
|
Planning |
|
| Orissa |
Angul Smelter power station units 9 and 10 |
National Aluminium Company |
240 |
1,419,288 |
|
Newly commissioned |
2010 |
| Orissa |
Angul Steel power station |
Jindal Steel & Power |
810 |
4,790,098 |
|
Construction |
2012 |
| Orissa |
Babandh power station |
Lanco |
1320 |
7,806,085 |
Supercritical |
Construction |
2014 |
| Orissa |
Balangir power station |
Sahara India Power Corporation |
1320 |
7,806,085 |
|
Early development |
|
| Orissa |
Baragaon power station |
Jinbhuvish Power Generations |
1320 |
7,806,085 |
|
Early development |
|
| Orissa |
Basundhara power station |
Mahanadi Coalfields Limited |
1600 |
9,461,921 |
Supercritical |
Early development |
|
| Orissa |
Bhadrak Ultra Mega Power Project |
Power Finance Corporation |
4000 |
23,654,803 |
Supercritical |
Planning |
|
| Orissa |
Bhubaneshwar Jasper power station |
Bhubaneshwar Power |
135 |
798,350 |
|
Planning |
|
| Orissa |
Brahmani power project |
NTPC & Coal India |
2000 |
11,827,402 |
|
Planning |
|
| Orissa |
Choudwar power station |
Indian Metals & Ferro |
30 |
177,411 |
Subcritical |
Newly commissioned |
|
| Orissa |
Choudwar power station |
Indian Metals & Ferro |
120 |
709,644 |
Subcritical |
Advanced development |
|
| Orissa |
Cuttack power station (KVK Nilachal) Phase I |
KVK |
350 |
2,069,795 |
|
Construction |
2014 |
| Orissa |
Cuttack power station (KVK Nilachal) Phase II |
KVK |
700 |
4,139,591 |
|
Planning |
|
| Orissa |
Cuttack power station (VISA Power) |
VISA Power |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| Orissa |
Darlipali Super Thermal Power Station |
NTPC |
1600 |
9,461,921 |
Supercritical |
Advanced development |
|
| Orissa |
Dhenkanal power station |
CESC |
1000 |
5,913,701 |
|
Planning |
|
| Orissa |
Gajmara Super Thermal Power Station |
NTPC |
1600 |
9,461,921 |
|
Advanced development |
|
| Orissa |
Ganjam power station |
SPR Infrastructure India |
2640 |
15,612,170 |
Supercritical |
Early development |
|
| Orissa |
Ghogarpalli Ultra Mega Power Project |
Power Finance Corporation |
4000 |
23,654,803 |
|
Planning |
|
| Orissa |
IB Thermal Power Station expansion |
Orissa Power Generation Corporation |
1320 |
7,806,085 |
|
Advanced development |
|
| Orissa |
Jharsuguda CPP power station Units 8 & 9 |
Vedanta Resources |
270 |
1,596,699 |
|
Newly commissioned |
2011 |
| Orissa |
Jharsuguda Ind-Barath power station Phase I |
Ind-Barath Power |
700 |
4,139,591 |
|
Construction |
2013 |
| Orissa |
Jharsuguda Ind-Barath power station Phase II |
Ind-Barath Power |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Orissa |
Jharsuguda Sterlite power station Unit 1-4 |
Sterlite Energy |
2400 |
14,192,882 |
Subcritical |
Newly commissioned |
2010 - 2012 |
| Orissa |
JR Power Project |
KSK Energy Ventures |
1980 |
11,709,128 |
|
Early development |
|
| Orissa |
Kamalanga power station phase I |
GMR Energy |
1050 |
6,209,386 |
|
Construction |
2013 |
| Orissa |
Kamalanga power station phase II |
GMR Energy |
350 |
2,069,795 |
|
Advanced development |
|
| Orissa |
Kishore Nagar Coal-to-Liquids Project |
Jindal Steel & Power |
1350 |
7,983,496 |
|
Planning |
|
| Orissa |
Malibrahmani power station |
Monnet Power Company |
1050 |
6,209,386 |
Subcritical |
Advanced development |
2014 |
| Orissa |
Naraj Marthapur power project |
Tata Power |
660 |
3,903,043 |
|
Planning |
|
| Orissa |
Navabharat II power station |
Essar Energy |
1200 |
7,096,441 |
|
Planning |
|
| Orissa |
Navabharat power station |
Essar Energy |
1050 |
6,209,386 |
|
Construction |
2014 |
| Orissa |
Neulapoi power station (Dhenkanal) |
CESC |
1200 |
7,096,441 |
|
Early development |
2015 |
| Orissa |
Paradip power plant |
Essar Energy |
120 |
709,644 |
Subcritical |
Construction |
|
| Orissa |
Pitamohul power station |
Ind-Barath Power |
1320 |
7,806,085 |
|
Planning |
|
| Orissa |
Randia power station |
Facor Power |
100 |
591,370 |
Subcritical |
Construction |
|
| Orissa |
Rengali power station |
Neyveli Lignite Corporation |
2000 |
11,827,402 |
|
Planning |
|
| Orissa |
Sakhigopal Ultra Mega Power Project |
Power Finance Corporation |
4000 |
23,654,803 |
|
Planning |
|
| Orissa |
Sri Ramchandrapur power project |
Dr. RKP Power |
120 |
709,644 |
Subcritical |
Planning |
|
| Orissa |
Srirampur Coal-to-Liquids Project |
Strategic Energy Technology Systems |
0 |
0 |
|
Planning |
|
| Orissa |
Sundargarh Ultra Mega Power Project (Lankahuda) |
NTPC |
4000 |
23,654,803 |
|
Planning |
|
| Orissa |
Talabira thermal station |
Neyveli Lignite Corporation, Mahanadi Coal Fields |
2000 |
11,827,402 |
|
Cancelled |
|
| Orissa |
Talcher Super Thermal Power Station second expansion |
NTPC |
1320 |
7,806,085 |
|
Planning |
|
| Orissa |
Talcher Thermal Power Station first expansion |
NTPC |
500 |
2,956,850 |
|
Planning |
|
| Orissa |
Wardha Naini Power Project |
KSK Energy Ventures |
1800 |
10,644,661 |
|
Early development |
|
| Punjab |
Gidderbaha power station |
Punjab State Electric Board |
2640 |
15,612,170 |
|
Deferred |
|
| Punjab |
GNDTP Bathinda Extn. Stage-II |
Punjab State Electric Board |
500 |
2,956,850 |
|
Planning |
|
| Punjab |
Gobindpura power station |
Indiabulls Power |
1320 |
7,806,085 |
|
Planning |
|
| Punjab |
Goindwal Sahib Thermal Power Plant |
GVK |
540 |
3,193,398 |
|
Construction |
2013 |
| Punjab |
Goindwal Sahib Thermal Power Plant expansion |
GVK |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| Punjab |
Guru Hargobind (Lehra Mohabbat) Power Station Stage III |
Punjab State Electric Board |
500 |
2,956,850 |
|
Planning |
|
| Punjab |
Mukerian power station |
Punjab State Power Corporation |
1320 |
7,806,085 |
|
Early development |
|
| Punjab |
Rajpura Thermal Power Project (Nalash) |
Punjab State Power Corporation |
1320 |
7,806,085 |
|
Construction |
2014 |
| Punjab |
Rajpura Thermal Power Project (Nalash) phase II |
Punjab State Power Corporation |
700 |
4,139,591 |
|
Planning |
|
| Punjab |
Ropar thermal plant expansion |
Punjab State Electric Board |
1320 |
7,806,085 |
|
Planning |
|
| Punjab |
Talwandi Sabo Power Project Unit 4 |
Sterlite Energy |
660 |
3,903,043 |
Supercritical |
Cancelled |
|
| Punjab |
Talwandi Sabo Power Project Units 1-3 |
Sterlite Energy |
1980 |
11,709,128 |
Supercritical |
Construction |
2014 |
| Rajasthan |
Banswara Cement power station |
India Cements |
20 |
118,274 |
|
Planning |
|
| Rajasthan |
Banswara Thermal Power Station |
Rajasthan RV Utpadan Nigam |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Rajasthan |
Barsingsar Thermal Power Project Unit 1 |
Neyveli Lignite Corporation |
125 |
739,213 |
|
Newly commissioned |
2010 |
| Rajasthan |
Barsingsar Thermal Power Project Unit 2 |
Neyveli Lignite Corporation |
125 |
739,213 |
|
Newly commissioned |
2011 |
| Rajasthan |
Bikaner power station |
OM Metals Infraprojects amd SPML |
70 |
413,959 |
|
Early development |
|
| Rajasthan |
Bithnok Thermal Power Project |
Neyveli Lignite Corporation |
250 |
1,478,425 |
|
Advanced development |
|
| Rajasthan |
Chhabra power station Unit 2 expansion |
Rajasthan RV Utpadan Nigam |
250 |
1,478,425 |
|
Newly commissioned |
2010 |
| Rajasthan |
Chhabra power station Unit 3-4 expansion |
Rajasthan RV Utpadan Nigam |
500 |
2,956,850 |
|
Construction |
2013 |
| Rajasthan |
Chhabra power station Unit 5-6 expansion |
Rajasthan RV Utpadan Nigam |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Rajasthan |
JSW Barmer (Jalipa Kapurdi) power station unit 2 |
JSW Energy |
135 |
798,350 |
Subcritical |
Newly commissioned |
2010 |
| Rajasthan |
JSW Barmer (Jalipa Kapurdi) power station units 3-4 |
JSW Energy |
270 |
1,596,699 |
Subcritical |
Newly commissioned |
2011 |
| Rajasthan |
JSW Barmer (Jalipa Kapurdi) power station units 5-8 |
JSW Energy |
540 |
3,193,398 |
|
Construction |
2013-2015 |
| Rajasthan |
JSW Barmer (Jalipa Kapurdi) power station units 9-10 |
JSW Energy |
270 |
1,596,699 |
|
Advanced development |
|
| Rajasthan |
Kalisindh Thermal Power Station |
Rajasthan RV Utpadan Nigam |
1200 |
7,096,441 |
Supercritical |
Construction |
2013 |
| Rajasthan |
Kalisindh Thermal Power Station Stage II |
Rajasthan RV Utpadan Nigam |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| Rajasthan |
Kawai Thermal Power Project |
Adani Power |
1320 |
7,806,085 |
Supercritical |
Construction |
2013 |
| Rajasthan |
Suratgarh Super Thermal Power Station Unit 7-8 |
Rajasthan RV Utpadan Nigam |
1320 |
7,806,085 |
|
Early development |
|
| Rajasthan |
Suratgarh Super Thermal Power Station Unit 9-10 |
Rajasthan RV Utpadan Nigam |
1320 |
7,806,085 |
Supercritical |
Early development |
|
| Rajasthan |
VS Lignite Plant |
KSK Energy Ventures |
135 |
798,350 |
Subcritical |
Newly commissioned |
2010 |
| Tamil Nadu |
Chennai power station I |
OPG Power Ventures |
77 |
455,355 |
Subcritical |
Newly commissioned |
2010 |
| Tamil Nadu |
Chennai power station II |
OPG Power Ventures |
77 |
455,355 |
Subcritical |
Construction |
2012 |
| Tamil Nadu |
Chennai power station III |
OPG Power Ventures |
160 |
946,192 |
Subcritical |
Advanced development |
2013 |
| Tamil Nadu |
Chennai power station III additional expansion |
OPG Power Ventures |
80 |
473,096 |
Subcritical |
Planning |
|
| Tamil Nadu |
Cheyyur Ultra Mega Power Project |
Coastal Tamil Nadu Power |
4000 |
23,654,803 |
|
Planning |
|
| Tamil Nadu |
Cuddalore power station |
Cuddalore Powergen Corporation |
1320 |
7,806,085 |
|
Deferred |
|
| Tamil Nadu |
Cuddalore SRM power station |
SRM Energy |
1980 |
11,709,128 |
Supercritical |
Planning |
|
| Tamil Nadu |
Ennore SEZ Super Critical Thermal Power Project (Vayalur) |
Tamil Nadu Generation and Distribution Corporation |
1600 |
9,461,921 |
Supercritical |
Planning |
|
| Tamil Nadu |
Ennore Thermal Power Station expansion |
Tamil Nadu Generation and Distribution Corporation |
1200 |
7,096,441 |
|
Planning |
|
| Tamil Nadu |
Jayamkondam power station |
Neyveli Lignite Corporation |
1600 |
9,461,921 |
|
Planning |
|
| Tamil Nadu |
Marakkanam Super Thermal Power Project |
NTPC |
4000 |
23,654,803 |
|
Planning |
|
| Tamil Nadu |
Mettur Thermal Power Station Stage III |
TANGEDCO |
600 |
3,548,220 |
|
Construction |
2012 |
| Tamil Nadu |
Nagai Power project (Nagapattinam) |
KVK Energy |
300 |
1,774,110 |
|
Planning |
2013 |
| Tamil Nadu |
New Neyveli Thermal Power Station |
Neyveli Lignite Corporation |
1000 |
5,913,701 |
|
Planning |
2015 |
| Tamil Nadu |
Neyveli TPS-II Expansion unit 1 |
Neyveli Lignite Corporation |
250 |
1,478,425 |
Circulating Fluidized Bed |
Newly commissioned |
2011 |
| Tamil Nadu |
Neyveli TPS-II Expansion unit 2 |
Neyveli Lignite Corporation |
250 |
1,478,425 |
Circulating Fluidized Bed |
Construction |
2013 |
| Tamil Nadu |
North Chennai Thermal Power Station - Stage-II Unit 1 |
Tamil Nadu Generation and Distribution Corporation |
600 |
3,548,220 |
Subcritical |
Construction |
2012 |
| Tamil Nadu |
North Chennai Thermal Power Station - Stage-II Unit 2 |
Tamil Nadu Generation and Distribution Corporation |
600 |
3,548,220 |
|
Construction |
2012 |
| Tamil Nadu |
Savarimangalam power station |
SPR Infrastructure India |
2640 |
15,612,170 |
|
Early development |
|
| Tamil Nadu |
Thoothukudi power station (IBPGL) |
Ind-Barath Power |
126 |
745,126 |
|
Newly commissioned |
2010 |
| Tamil Nadu |
Thoothukudi power station (IBPGL) expansion |
Ind-Barath Power |
63 |
372,563 |
|
Planning |
|
| Tamil Nadu |
Thoothukudi power station (IBTPL Hanakon replacement) |
Ind-Barath Power |
300 |
1,774,110 |
|
Early development |
|
| Tamil Nadu |
Tirunelveli power station |
India Cements |
50 |
295,685 |
|
Planning |
|
| Tamil Nadu |
Melamaruthur Power Station Phase I |
Coastal Energen |
1200 |
7,096,441 |
Subcritical |
Construction |
2013 |
| Tamil Nadu |
Melamaruthur Power Station Phases II and III |
Coastal Energen |
1600 |
9,461,921 |
Supercritical |
Planning |
|
| Tamil Nadu |
Tuticorin power station (Ind-Barath) Phase I |
Ind-Barath Power |
660 |
3,903,043 |
Supercritical |
Advanced development |
|
| Tamil Nadu |
Tuticorin power station (Ind-Barath) Phase II |
Ind-Barath Power |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Tamil Nadu |
Tuticorin Thermal Power Project |
Tamil Nadu Generation and Distribution Corporation and Neyveli Lignite Corp |
1000 |
5,913,701 |
|
Construction |
2013 |
| Tamil Nadu |
Udangudi power station |
Tamil Nadu Generation and Distribution Corporation and Bharat Heavy Electricals Limited |
1600 |
9,461,921 |
Supercritical |
Advanced development |
|
| Tamil Nadu |
Uppur power station (Thiruvadanai) |
Tamil Nadu Generation and Distribution Corporation |
1600 |
9,461,921 |
Supercritical |
Early development |
|
| Tamil Nadu |
Vallur Thermal Power Plant Unit 1 |
NTPC and Tamil Nadu Generation and Distribution Corporation |
500 |
2,956,850 |
|
Newly commissioned |
2012 |
| Tamil Nadu |
Vallur Thermal Power Plant Units 2 and 3 |
NTPC and Tamil Nadu Generation and Distribution Corporation |
1000 |
5,913,701 |
|
Construction |
2013 |
| Uttar Pradesh |
Amauli Fatehpur power station |
Uttar Pradesh Power Corporation and Neyveli Lignite Corporation |
1980 |
11,709,128 |
|
Construction |
2015 |
| Uttar Pradesh |
Anpara power station (Lanco) |
Lanco |
1200 |
7,096,441 |
Subcritical |
Newly commissioned |
2011 |
| Uttar Pradesh |
Anpara-C power station |
UP Rajya Vidyut Nigam Ltd |
1200 |
7,096,441 |
|
Newly commissioned |
2011 |
| Uttar Pradesh |
Anpara-D power station Unit I |
UP Rajya Vidyut Nigam Ltd |
500 |
2,956,850 |
|
Construction |
2014 |
| Uttar Pradesh |
Anpara-D power station Unit II |
UP Rajya Vidyut Nigam Ltd |
500 |
2,956,850 |
|
Construction |
2014 |
| Uttar Pradesh |
Anpara-E power station |
UP Rajya Vidyut Nigam Ltd |
1320 |
7,806,085 |
|
Planning |
|
| Uttar Pradesh |
Auraiya IGCC power station |
NTPC and BHEL |
300 |
1,774,110 |
IGCC |
Deferred |
|
| Uttar Pradesh |
Auraiya Unitech power station |
Unitech Machines |
250 |
1,478,425 |
|
Planning |
|
| Uttar Pradesh |
Bara Thermal Power Project Phase I |
Jaiprakash Power Ventures |
1980 |
11,709,128 |
|
Construction |
2014 |
| Uttar Pradesh |
Bara Thermal Power Project Phase II |
Jaiprakash Power Ventures |
1320 |
7,806,085 |
|
Planning |
|
| Uttar Pradesh |
Bargarh power station |
Bajaj Hindusthan |
1980 |
11,709,128 |
|
Early development |
|
| Uttar Pradesh |
Barkera Mill power station |
Bajaj Hindusthan |
80 |
473,096 |
|
Planning |
|
| Uttar Pradesh |
Bhognipur power station |
Lanco |
2640 |
15,612,170 |
|
Early development |
|
| Uttar Pradesh |
Bilhaur Super Thermal Power Plant |
NTPC |
1320 |
7,806,085 |
|
Early development |
|
| Uttar Pradesh |
Chola power station |
Tata Power |
1320 |
7,806,085 |
|
Planning |
|
| Uttar Pradesh |
Dopaha Thermal Power Plant |
Uttar Pradesh Power Corporation |
1980 |
11,709,128 |
Supercritical |
Early development |
|
| Uttar Pradesh |
Fatehpur power station |
Uttar Pradesh Power Corporation |
1320 |
7,806,085 |
|
Planning |
2015 |
| Uttar Pradesh |
Feroz Gandhi Unchahar Power Project Stage IV |
NTPC |
500 |
2,956,850 |
|
Planning |
|
| Uttar Pradesh |
Harduaganj TPS Extn - Stage III (Kasimpur) |
Uttar Pradesh Rajya Vidyut |
660 |
3,903,043 |
Supercritical |
Planning |
|
| Uttar Pradesh |
Harduaganj TPS Extn Stage II Unit 8 (Kasimpur) |
Uttar Pradesh Rajya Vidyut |
250 |
1,478,425 |
|
Newly commissioned |
2011 |
| Uttar Pradesh |
Harduaganj TPS Extn Stage II Unit 9 (Kasimpur) |
Uttar Pradesh Rajya Vidyut |
250 |
1,478,425 |
|
Newly commissioned |
2012 |
| Uttar Pradesh |
Jawaharpur Thermal Project |
Jawaharpur Vidyut Utpadan Nigam |
1320 |
7,806,085 |
|
Planning |
2013 |
| Uttar Pradesh |
Karchana Thermal Power Project |
Jaypee Group |
1980 |
11,709,128 |
|
Deferred |
|
| Uttar Pradesh |
Lalitpur power project (Mirchawar) |
Bajaj Hindusthan |
1980 |
11,709,128 |
|
Early development |
2014-2015 |
| Uttar Pradesh |
Meja Thermal Power Project |
NTPC and Uttar Pradesh Rajya Vidyut |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2016 |
| Uttar Pradesh |
NCTPP IGCC demonstration (Dadri) |
NTPC |
100 |
591,370 |
|
Planning |
|
| Uttar Pradesh |
NCTPP Stage II (Dadri) |
NTPC |
980 |
5,795,427 |
|
Newly commissioned |
2010 |
| Uttar Pradesh |
Obra thermal station extension |
UP Rajya Vidyut Nigam Ltd |
1600 |
9,461,921 |
|
Planning |
|
| Uttar Pradesh |
Panki Thermal Power Station extension |
UP Rajya Vidyut Nigam Ltd |
250 |
1,478,425 |
|
Planning |
|
| Uttar Pradesh |
Parichha power station Unit 5 |
Uttar Pradesh Rajya Vidyut |
250 |
1,478,425 |
|
Newly commissioned |
2012 |
| Uttar Pradesh |
Parichha power station Unit 6 |
Uttar Pradesh Rajya Vidyut |
250 |
1,478,425 |
|
Construction |
2013 |
| Uttar Pradesh |
Rihand III power station Unit 5 |
NTPC |
500 |
2,956,850 |
|
Newly commissioned |
2012 |
| Uttar Pradesh |
Rihand III power station Unit 6 |
NTPC |
500 |
2,956,850 |
|
Construction |
2013 |
| Uttar Pradesh |
Rosa Thermal Power Plant |
Reliance Power |
1200 |
7,096,441 |
|
Newly commissioned |
2010-2012 |
| Uttar Pradesh |
Singrauli Super Thermal Power Station Stage III |
NTPC |
500 |
2,956,850 |
|
Planning |
|
| Uttar Pradesh |
Tanda power station expansion |
NTPC |
1320 |
7,806,085 |
|
Planning |
|
| Uttar Pradesh |
Welspun Energy Mirzapur power station |
Welspun Energy |
1320 |
7,806,085 |
|
Early development |
|
| Uttar Pradesh |
Welspun Ghazipur project |
Welspun Energy |
1320 |
7,806,085 |
|
Planning |
2015 |
| West Bengal |
Adra Purulia power station |
NTPC and Indian Railways |
1320 |
7,806,085 |
|
Cancelled |
|
| West Bengal |
Bakreswar Thermal Power Station Unit 6 |
West Bengal Power Development Corp. |
660 |
3,903,043 |
|
Planning |
|
| West Bengal |
Balagarh power station |
CESC |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| West Bengal |
Bankura Concast power station |
Concast Bengal Industries |
20.5 |
121,231 |
|
Planning |
|
| West Bengal |
Bhushan Steel West Bengal project |
Bhushan Steel |
1000 |
5,913,701 |
|
Deferred |
|
| West Bengal |
Durgapur Projects Limited power station unit 8 |
Durgapur Projects Limited |
250 |
1,478,425 |
|
Construction |
2014 |
| West Bengal |
Durgapur Steel City power station |
Damodar Valley Corporation |
1000 |
5,913,701 |
|
Newly commissioned |
2011-2012 |
| West Bengal |
Farakka III power station (Unit 6) |
NTPC |
500 |
2,956,850 |
|
Newly commissioned |
2011 |
| West Bengal |
Haldia Energy power station Phase 1 |
CESC |
600 |
3,548,220 |
|
Construction |
2014 |
| West Bengal |
Haldia Energy power station phase 2 |
CESC |
1400 |
8,279,181 |
|
Planning |
|
| West Bengal |
Katwa Super Thermal Power Project (NTPC) |
NTPC |
1600 |
9,461,921 |
|
Deferred |
|
| West Bengal |
Larsen & Tubro power station |
Larsen & Tubro |
3200 |
18,923,843 |
|
Planning |
|
| West Bengal |
Mejia power station phase II units 1 and 2 |
Damodar Valley Corporation |
1000 |
5,913,701 |
|
Newly commissioned |
2010-2011 |
| West Bengal |
Raghunathpur Thermal Power Station phase I |
Damodar Valley Corporation |
1200 |
7,096,441 |
Subcritical |
Construction |
2013 |
| West Bengal |
Raghunathpur Thermal Power Station phase II |
Damodar Valley Corporation |
1320 |
7,806,085 |
Supercritical |
Planning |
|
| West Bengal |
Sagardighi Thermal Power Station Phase II |
West Bengal Power Development Corp. |
1000 |
5,913,701 |
Subcritical |
Construction |
2014 |
| West Bengal |
Salboni 1 (CPP-IV) |
JSW Bengal Steel |
300 |
1,774,110 |
|
Construction |
2014 |
| West Bengal |
Salboni 2 and 3 |
JSW Energy |
1320 |
7,806,085 |
Supercritical |
Advanced development |
2016-2017 |
| West Bengal |
Santaldih Thermal Power Station unit 6 |
NTPC |
250 |
1,478,425 |
Subcritical |
Newly commissioned |
2011 |
| West Bengal |
Santildih Thermal Power Station units 7 and 8 |
NTPC |
1320 |
7,806,085 |
Supercritical |
Cancelled |
|