Freeport Plant

From SourceWatch
Jump to: navigation, search

This article is part of the Coal Issues portal on SourceWatch, a project of CoalSwarm and the Center for Media and Democracy. See here for help on adding material to CoalSwarm.

In June 2008, Hunton Energy submitted an air permit application to the Texas Commission on Environmental Quality (TCEQ) to build a $2.4 billion gasification plant in Freeport, Texas.

The site for the proposed plant was recently relocated to take advantage of deep water, electrical transmission and natural gas infrastructure. The new location is adjacent to the Dow Chemical Oyster Creek Facility. The Freeport plant will use a gasification process to convert petroleum coke into Synthetic Natural Gas (SNG), which will be sold to Dow Chemical. The plant will also use steam turbines to produce additional power from its byproduct steam. Hunton Energy plans to sell all CO2 emissions produced in the gasification process to a CO2 consolidator for sequestration in oil and gas fields. The plant is expected to be operational in 2012.[1]

On March 4, 2009, the TCEQ issued a final air permit for the Freeport plant.[2]

In February 2012, the Sierra Club reported that Hunton Energy had not been able to finalize an agreement with Dow Chemical and would no longer pursue the plant.[3]

Project Details

Sponsor: Hunton Energy
Location: Freeport TX
Capacity:
Type: Gasification (petroleum coke to Synthetic Natural Gas)
Projected in service: 2012
Status: Cancelled 2012

Financing

Citizen Groups

Resources

References

  1. "Stopping the Coal Rush", Sierra Club, accessed November 2008. (This is a Sierra Club list of new coal plant proposals.)
  2. "Stopping the Coal Rush", Sierra Club, accessed May 2009. (This is a Sierra Club list of new coal plant proposals.)
  3. "Stopping the Coal Rush", Sierra Club, accessed August 2012 (This is a Sierra Club list of new coal plant proposals.)

Related SourceWatch Articles

<us_map redirect="{state} and coal"></us_map>

External links