Binga power station

From SourceWatch
(Redirected from Lusulu power station)
Jump to: navigation, search

Binga power station, also known as the Lusulu power station, is a proposed 2,100-megawatt (MW) coal-fired power station in Zimbabwe. The first phase would be 2 x 350 MW.

Location

The map below shows Binga, the approximate location where the plant would be built near the Lusulu coal fields.

Loading map...

Background

In 2012 a French consortium was granted a licence by the Zimbabwean government to build a US$3 billion thermal power plant in the country. The 2,000 MW power station would be situated in the Lusulu coal fields at Binga, in the Matabeleland North province of Zimbabwe. The coal fields have an estimated 1.2 billion tonnes of coal reserves. The expected commissioning date was 2016.[1]

PER Lusulu Power is the company pursuing the project. In August 2014 its CEO said the company had bought coal plants from the European company EDF and would be transporting them to Zimbabwe to construct the power station. Construction was planned to begin in 2015, with four units of 500 MW each. Unit 1 was planned for operation in 2018.[2]

In July 2015 Lusulu Power secured a US$950 million loan from China and signed an EPC (engineering, procurement, and construction) agreement with China State Construction Engineering Corporation (CSCEC) for the first phase of a 600-MW coal-fired power plant, a first phase that is eventually planned to reach 2,000 MW. Construction of phase one was planned to begin in early 2016, at a cost of US$1.1 billion. Commissioning was planned for 2019, and would include construction of roads, transmission lines and related infrastructure.[3][4]

As of May 2017, the project had changed to 2,100MW: 1A of 350MW; 1B of 350MW; phase 2 of 700MW; and phase 3 of 700MW. The total development cost of the phase 1A project is estimated to be US$1billion. The company's website stated that the following milestones have been completed:[5]

  • Power Generation Licence Concession.
  • Transmission licence.
  • PER has been accorded to be a project of national status.
  • Implementation Agreement with the Government have been granted and signed.
  • The Environmental Social Impact Assessment has been approved.
  • Coal Supply Agreements have been signed with the Coal Supplier.
  • Water supply has been agreed.

As of December 2018, the company's website stated that financial close and construction of Phase 1A (350MW) would take place in H2 of 2019, with commissioning planned for H2 of 2022 and commercial generation in Q1 of 2023.[6]

Project Details

  • Sponsor: PER Lusulu Power
  • Parent company:
  • Location: Binga, Matabeleland North province, Zimbabwe
  • Coordinates: -17.616667, 27.333 (approximate)
  • Status: Unit 1A: Permitted; Unit 1B: Permitted; Units 2-4: Announced
  • Gross Capacity: 2,100 MW (Unit 1A: 350 MW, Unit 1B: 350 MW; Additional units 3 x 700 MW[5]
  • Type: Ultra-supercritical
  • Projected in service: 2022 (Unit 1)
  • Coal Type:
  • Coal Source: Lusulu coal field
  • Source of financing: debt finance via Sinosure Buyers Credit Facility with Bank of China[5]