Opole Power Station is a 1,480-megawatt (MW) coal power station in Opole, Poland, operated by the state-owned Polska Grupa Energetyczna (PGE Group). It began operating in 1993-1997.[1]

An 1800 MW expansion of the station began construction in 2014.

Location

The undated satellite photo below shows the power station in Opole.

Loading map...

Expansion plans

PGE Group planned to add two hard coal fired 900 MW supercritical power units (5 and 6). PGE's 2012 strategy indicated one 900MW unit commissioned and scheduled for 2017, with the second unit planned for 2018.[2] The plant would cost $3.7 billion. The consortium to build Opole includes Polimex, Rafako (a unit of PBG), and Mostostal Warszawa, which is the Polish unit of Spanish firm Acciona.[3]

PGE had to delay the construction of the units after a court blocked the investment following an appeal by ecologists. In October 2012 a Polish court ordered the re-examination of a block, sending the case back to a lower court.[4]

In April 2013, PGE announced that it had decided to cancel the expansion plans, citing weak electricity demand and falling electricity prices.[5]

However, in January 2014 PGE announced that construction would begin in February on 1,800 megawatts of new coal-fired generating capacity at the Opole station. The $3.78 billion expansion will be designed by the French multinational Alstom. The first unit is expected for 2018 and the second in 2019. There are reports that the company is being politically pressured to proceed with the expansion despite rejecting it in April 2013 as unprofitable.[6]

The ultra-supercritical boilers used by the plant are being manufactured in Wuhan, China, and supplied by Alstom Wuhan Boiler Company.[7]

Project Details

  • Sponsor: PGE
  • Parent company:
  • Developer: Alstom
  • Location: Opole, Poland
  • Coordinates: 50.75182,17.88196 (exact)
  • Status: Construction
  • Capacity: 1800 MW (Units 5&6: 900 MW)
  • Type: Ultra-supercritical
  • Start date:
    • Unit 5: 2018
    • Unit 6: 2019
  • Coal Type: Hard coal
  • Coal Source:
  • Source of financing: