Troubled Indian Coal Plant Construction Sites

From SourceWatch
Jump to: navigation, search

This article is part of the Coal Issues portal on SourceWatch, a project of CoalSwarm and the Center for Media and Democracy. See here for help on adding material to CoalSwarm.

This article is part of the CoalSwarm coverage of India and coal.
Sub-articles:

In late 2016, at least 31 coal-fired power plants under construction at 13 locations totalling 12,725 MW were on hold, most often due to lack of financing. Shown at the bottom of this page are satellite photos from one such project, Cuttack KVK Nilachal power station in Odisha, where work has been suspended since 2013, as shown in photos archived on Google Earth.

Troubled projects

The table below is based on the India Ministry of Power's "Broad Status Report," October 2016.

Project Other names Number of Units Halted MW Halted Issues Ministry of Power Notes State
Bhavanapadu Thermal Power Project 2 1320 Finances, Civil Resistance "Presently work is held up at site due to financial issues." "Law & Order problem." Andhra Pradesh
Raigarh project (VISA Power) Deveri or VISA 2 1200 Finances "Work is on hold due to financial crunch." Chhattisgarh
Chandwa Power Project Matrishri Usha Jayaswal 4 1080 Civil Resistance "Work held up due to payment issue to BHEL since 11/12." Jharkhand
Tori power plant 2 1200 Finances, Civil Resistance, Water Availability, Coal, Permit "Presently no work is in progress due to financial constraints" Jharkhand
Gorgi power station 1 660 Finances "Work is on hold at site due to Financial crunch being faced by the developer." Madhya Pradesh
Amravati Thermal Power Project, Phase II 5 1350 Finances "Due to financial constraints project has been put on hold." Maharashtra
Nasik RattanIndia Thermal Power Project Phase II 3 810 Finances "Work at site has been put on hold since long back" Maharashtra
Cuttack KVK Nilachal power station 1 350 Law and order problem "No work is under progress presently." Odisha
Bijora power station 2 600 Finances "Work at site put on hold due to financial crunch." Maharashtra
Malibrahmani power station 2 1050 Finances "Work held up due to financial constraints" Odisha
Gadarwara power station (BLA) Niwari 1 45 Finances "Presently work at site has been put on hold." Madhya Pradesh
Banka Power Project Siriya 4 2640 Coal "Presently no work is in progress at site." Bihar
Lanco Amarkantak Thermal Power Project Phase II 2 1320 Finances, Land Acquisition "Presently no work is going at the site due to financial problems." Chhattisgarh
Total 31 12,725

Cuttack KVK Nilachal power station - Odisha

As shown in satellite photos spanning the period from April 2012 to October 2016, work on the project has not progressed in over four years.


Cuttack KVK Nilachal power station, April 9, 2012 (Google Earth)
Cuttack KVK Nilachal power station, October 31, 2013 (Google Earth)
Cuttack KVK Nilachal power station, November 24, 2014 (Google Earth)
Cuttack KVK Nilachal power station, October 20, 2016 (Google Earth)

Babandh power station

The Broad Status Report does not include this project among those considered on hold; however, construction has been underway since 2011 and shows little progress since 2013. The Broad Status Report says that work is "almost held up due to financial constraint."[1]

Babandh power station 4-16-13 (Google Earth)
Babandh power station 2-3-14 (Google Earth)
Babandh power station 2-23-15 (Google Earth)
Babandh power station 12-14-16 (Google Earth)

Tuticorin power station (Ind-Barath)

The Broad Status report does not describe this project as being on hold; however, the pace of construction has slowed to a crawl. While the report states that construction has been underway on the project since 201, archival photography on Google Earth and by records of expenditures reported by the Ministry of Energy show that the project has not progressed beyond foundation works. Of an estimated project cost of 359,500 Lakh, 150,00 were spent through the end of FY 2014/15, followed by the expenditure of only 500 Lakh in FY 2015/2016. Based on the low pace of recent expenditures, the project appears to be on hold.[2]


Articles and resources

References

  1. "MONTHLY REPORT ON BROAD STATUS OF THERMAL POWER PROJECTS IN THE COUNTRY," Ministry of Power, December 2016.
  2. "Broad Status Report," India Central Electrical Authority, March 2017